FAQ - Tilt Up

What is the typical thickness of a panel?

The minimum thickness for commercial walls is generally 5½ inches with 7¼ inches the most typical thickness reinforced with 1.3 to 2.5 psf of reinforcing.

What is the minimum size building that is economical?

Some as small as 5,000 square feet can be economical, if they are relatively tall. Several small buildings clustered together may also prove economical. Special finishes on the walls, such as exposed aggregate or form liners may make Tilt-Up an economical choice.

What is the minimum height building that is economical?

Panels up to 96 feet in height have been used in some areas, but special cranes and spreader bars are required for panels over 30 feet in height. It is generally better to have the panels all nearly the same height and less than 30 feet.

Are there any limits to the number or location of openings?

There is no real limit to the number or location of openings, but their location can be critical. Openings closer than the minimum from the end of the panel supporting a concentrated roof load can add considerable reinforcing, thickened concrete or steel columns. The minimum distance is one-eighth the eave height, or two feet, whichever is less.

What size crane is needed to lift the panel?

It is best to let the crane company determine this, based on the size and weight of panels involved. A rule of thumb for the size, however, is two to three times the weight of the panel.

Are there any site conditions that limit Tilt-Up?

Yes, the following should be considered: Access by the crane to the job site. Relatively flat terrain to allow the crane operation. Any power lines, ditches, railroad tracks, or other obstructions which limit crane operation. Other buildings very close to where panels must be placed.

What is the fire resistance of a Tilt-Up panel?

The fire resistance of Tilt-Up walls is easily referenced and/or calculated in the current UBC and IBC codes. Fire resistance is related to an R rating that determines time duration based on the thickness and type of material. Whether a solid concrete panel or an insulated sandwich panel, Tilt-Up fire resistance can be determined with little effort.

The following table is reprinted from the data contained in both the UBC and IBC codes. It shows the relative thickness required for each aggregate type to meet the listed fire resistivity rating.

NEWS

  • 29 Jul 2023

    ESPT AWARDED NEW SOIL NAIL SUPPLY DESIGN AND SUPERVISION IN SAUDI ARABIA

    ESPT Saudi Arabia awarded a new design,  supply supervision and testing of micropiles in Khobar, Saudi Arabia, the so...

  • 04 Mar 2021

    Esolution Awarded Supply and installation of Pre-tension Girders in Cairo-Egypt

    Mostaqbal City Bridge project been designed as Pre-tensioned Girders onsite precast concrete, where Esolution have supplie...

  • 04 Mar 2021

    Esolution Saudi Arabia Completes additional Multi strand Anchorage testing

    Esolution construction and Engineering have taken extra mile for Qaulity assurance for bridges work, whereas Esolution bee...

  • 15 Jan 2021

    ESPT- Dubai is now functioning with European Approved Multi-strand system

    ESPT Dubai - United Arab Emirates is introducing multistrand anchorages system 2 to 37 strands European approved system in...

  • 19 May 2020

    Esolution Awarded a new Bridge Posttensioning work in Saudi Arabia

    esolution construction and Engineering Saudi Arabia have been awarded supply and application of posttension concrete works...

  • 19 May 2020

    Esolution Receives ministry of transportation Approval in Saudi Arabia

    Esolution construction and Engineering receives min...

  • 05 Mar 2020

    ESPT Approved as Posttension supplier in Dubai

    ESPT Posttension concrete supplies are now being approved with

  • 04 Oct 2019

    Esolution adds bars to its portfolio

    Esolution adds Prestressing bars to its products range to the market, the application range as follows:

  • 04 Oct 2019

    esolution adds new range of PT anchorages to its profile

    esolution construction and Engineering in Saudi Arabia and Dubai is now offering a new range of European technical approve...

  • 04 Oct 2019

    esolution adds new range of PT anchorages to its profile

    esolution construction and Engineering in Saudi Arabia and Dubai is now offering a new range of European technical approve...

  • 11 Feb 2019

    Esolution Dubai branch completed a design of new structure

    esolution construction and Engineering Dubai branch completed a design of new structure that been re...

  • 16 Aug 2018

    esolution Dubai completes a four new Precast concrete buildings design

    esolution Dubai completes a two new Precast concrete buildings design includes cast at site parts of the structures, the s...

  • 16 Aug 2018

    esolution construction and Engineering Dubai awarded Alloft Hotel design of posttension concrete slabs

    esolution construction and Engineering Dubai awarded Alloft Hotel design of posttension concrete slabs, the porject consis...

  • 30 Mar 2018

    Esolution receives Dubai Municipality approval for construction of Posttension concrete slabs in Dubai

    Esolution Dubai recieves Dubai muncapility approval fo...

  • 23 Dec 2017

    Esolution complete the design of precast concrete structure using Revit

    esolution construction and Engineering design team completes the design, segmentation and fabrication drawings for precast...

  • 23 Dec 2017

    esolution awarded a new Posttension concrete project in Alexandria-Egypt

    esolution awarded a new project for the design and construction of posttension concrete in Alexandria-Egypt, the project b...

  • 23 Dec 2017

    esolution awarded a new Posttension concrete resturant project in Dammam-Kingdom of Saudi Arabia

    esolution awarded a new project for the design and construction of posttension concrete Dammam- Kingdom of Saudi Arabia, t...

  • 21 Oct 2017

    esolution completes posttension work in Saudi Arabia-Makkah, Islamic Relief tower-10

    Esolution construction & Engineering completes the de...

  • 21 Oct 2017

    esolution Design team rectifies the design of hotel building in Jeddah

    The hotel complicated design has been awarded to esolutio...

  • 29 Nov 2016

    esolution completes RAJHI Showrooms in Riyadh

    AlRajhi showroom in Riyadh is four floor building with an area per floor of 4000 Square meters, the challange in the desig...

  • 08 Mar 2016

    esolution spoke to construction week online magazine on PT construction in GCC

    esolution construction and Engineering spoke to construction week online magazine on PT construction in GCC, esolutio...

  • 17 Jan 2016

    Esolution accepted block work contract in Lulu hyper Market In Saudi Arabia

    Lulu Hypermarket 

    LuLu Hypermarket, the retail division of the multidimensional and multinat...

  • 13 Jan 2016

    esolution Management to Upscale Egypt's Team skills to train them on the Building information modeling

    esolution Management recognizes the importance of people training and development and to align the team in different ...

  • 13 Jan 2016

    Rahaf Al Masha'ar hotel in Mecca-Saudi Arabia is now functioning

    esolution construction and engineering compeleted the design and construction of the hotel in six months, the tower redesi...

  • 12 Jan 2016

    Tilt up education at BIG-05, Kuwait

    y: Mohamed Zaid, CEng. M. ASCE, Design Manager , Associate member – ACI-551 / ACI-...

  • 11 Jan 2016

    TILT-UP CONCRETE CONSTRUCTION AWARENESS RAMPED UP IN EMERGING COUNTRIES

    By: Mohamed Zaid, CEng. M. ASCE

    When compared to other d...

  • 11 Jan 2016

    INTERNATIONAL ISLAMIC RELIEF TOWER IN MECCA - THE CHALLENGE

    The porject is located in Mecca with three towers on same basement , its very traditional con...

  • 22 May 2015

    Arabian Business :Rotana to open first two Centro hotels in Saudi , esolution awarded the posttension concrete construction of the project

    Arabian Business on Rota...

  • 22 May 2015

    esolution construction & Engineering completes the first six slabs - Rotana Hotel in 2 months

    esolution contruction & ENgineering compelets the first six slabs in two months , expecting the contract compilation w...

  • 04 May 2015

    esolution Construction and Engineering merges with esolution investment

    esolution Construction and Engineering merges with esolution investment and starts to work in real state in Egypt , the tw...

  • 03 May 2015

    e-solution Supports charity health Care in Cairo-Egypt

    Charity care

    Charity care is a health care service provided for free or at reduced prices to low income pat...

  • 29 Mar 2015

    Tilt up education at BIG-05, Dubai

    By: E-Solution / Mohamed Zaid, CEng. M. ASCE, Associate member – ACI-551 / ACI-423

    The B...

  • 02 Feb 2015

    Cooperation Council for the Arab States of the Gulf building in Riyadh - design and construction of posttension concrete slabs by Esolution

     Cooperation Council for the Arab States of the Gulf

     مجلس التعاون لدول ...

  • 01 Feb 2015

    esolution Starts working on LULU Hypermarket- Riyadh

    Esolution has started work on LULU’s hyper market in Riyadh-Kingdom of Saudi Arabia , the project with area of 120 t...

  • 01 Dec 2014

    International Islamic Relief Constructs new tower in Mecca for orphans - Structure design , PT design and supply by esolution

    The International Islamic Relief Organization,  هيئة الإغاثة ا...

  • 02 Oct 2014

    Gulf Business - UAE’s Arabtec To Launch Phase 1 Of Mega Egypt Housing Project By Year-End- Design Shared by esolution

  • 01 Oct 2014

    esolution introduces BIM solution in Saudi Arabia

    Building information modeling

    Building Information Modeling (BIM) is changing how buildings, infrastructure, and...

  • 03 Jun 2014

    esolution construction and Engineering design affordable housing units in Egypt-Cairo using aluminium concrete forms

  • 02 Jun 2014

    AL-JOUF UNIVERSITY - FACULTY OF MEDICINE - POST TENSION CONCRETE FLOOR SLABS

    l-Jouf region is located in the northwestern part of the Kingdom of Saudi Arabia, and an area (139.00) km, a population of...

  • 04 Mar 2014

    Pearl Compound in Al- Khobar-Saudi Arabia

    esolution construction & Engineering awarded the design and construction of post tension floors in Pearl compound , th...

  • 01 Sep 2013

    esolutuion PT completes 125 slabs construction in Rabia Community -Riyadh

    Watch Video 

     esolution construction and Engineering awarded the&...

  • 01 Jan 2013

    esolution run a presentation on posttension concrete water tanks to ministry of water and electricity - Riyadh Saudi Arabia

    esolution  run a presentation on posttension concrete water tanks to ministry of water and electricity - Riyadh Saudi...

  • 04 Nov 2012

    Hilton - Obikan Towers post-pensioning concrete floors by Esolution - Riyadh

    solution construction and Engineering re-evaluated the design of the tower as desired by the client to enure that original...

  • 12 Jul 2012

    FACULTY OF ENGINEERING-AL TAEF

    Esolution construction & Engineering approved by ministry of higher education as sub cons...

  • 01 Mar 2012

    Taif University - Faculty of Engineering - design and detailing by esolution - sub consultancy service

    esolution construction and Engineering hired as a sub consultant to value Engineer the project , reducing the cumlative co...

  • 02 Feb 2012

    Arabnews - Hilton Worldwide has announced the signing of a management agreement with Obeikan Real Estate Development Company

    Hilton Obikan - Riyadh